Following the current progress, F-Ville 2, the second campus of FPT Software in Hoa Lac High-Tech Park has completed over 70% and will be put into use on September 13th, 2016, marking 28th Anniversary of FPT Corporation.

HoaLac-High-Tech

With total $15 million investment and covering over 6 hectars, F-Ville 2 is considered as the first and also the largest project within the Software Compound of Hoa Lac High-Tech Park that is put into use.

HoaLac-High2

Despite a tight timeline and other difficulties, more than 300 workers and construction engineers have managed the project very well and worked continuously onsite to ensure a constant progress

HoaLac-Hight3

F-Ville 2 is expected to meet the growing HR demand of FPT Software by providing a workplace for over 3,000 employees.

HoaLac-High4

The campus includes an office compound with a total floor area of ​​nearly 28,000 m2, complete auxiliary functions as expert guest rooms, the cafeteria, and spacious entertainment & relaxing facilities.

HoaLac-Hight4

Earlier, F-Ville 1 project was inaugurated and put into operation in November, 2013 with a total investment of about $10 million, which included an office compound with a total floor area of 16,000 m2, offering workspace for about 1700-1900 employees, a large dining area and outdoor leisure & sport areas such as swimming pools, mini-soccer field with artificial turf.